Skip to main content

Federal Register: final rule

Clean Water Act Hazardous Substance Facility Response Plans: Compliance Date Delay and Changes To Reflect Administration Policy

Federal Register published "Clean Water Act Hazardous Substance Facility Response Plans: Compliance Date Delay and Changes To Reflect Administration Policy" on 2026-10-13. First seen on Kresmion 2026-10-26 18:25 UTC.

As of . Source: www.federalregister.gov. Method and limitations.

The record

Publisher
Federal Register
Agency
Environmental Protection Agency
Source
Federal Register
Kind
Federal Register: final rule
Jurisdiction
United States
Topics
Environment
Importance
Notable, the middle of three tiers Kresmion sets by fixed rules from the source's own fields
Published (source time)
2026-10-13 (the source gives a date only)
First seen on Kresmion
2026-10-26 18:25 UTC

The original

Open the original on www.federalregister.gov

Source: Federal Register (federalregister.gov). U.S. government work, public domain.

The publisher's summary

The Environmental Protection Agency (EPA) is finalizing an extension to the compliance date for Facility Response Plans (FRPs) required by the Clean Water Act (CWA) addressing potential worst-case discharges of CWA hazardous substances. These requirements apply to onshore non-transportation-related facilities that could reasonably be expected to cause substantial harm to the environment from a CWA hazardous substance worst-case discharge to navigable waters, adjoining shorelines, or the exclusive economic zone. This action is also finalizing language modifications to remove references to climate change and environmental justice in the FRP requirements to align with Executive Order 14148 of January 20, 2025. EPA is revising the compliance deadlines in light of serious concerns that facilities may be unable to comply with the relevant requirements by the existing deadline. These changes are necessary to allow the Agency to consider implementation and compliance assistance tools that regulated facilities may be able to take advantage of when complying with the new requirements, and to ensure proper planning for all communities while promoting a science-based and risk-based approach to planning. EPA also recognizes that a delay would provide time for EPA to consider whether revisions are necessary before facilities must comply.

The publisher's words, as published.

Federal Register document

Document number
2026-20849
Document type
Rule
Status
Published

Cite this data

Kresmion stores the publisher's own title, the source's time and the time Kresmion first saw it, and checks the primary link 1, 7 and 30 days after first sight. Kresmion adds no text of its own.

Upstream: Federal Register

Kresmion, "Clean Water Act Hazardous Substance Facility Response Plans: Compliance Date Delay and Changes To Reflect Administration Policy", data as of 2026-10-13, https://kresmion.com/record/7145. Upstream data: Federal Register.

Link to this data (HTML):

<a href="https://kresmion.com/record/7145">Clean Water Act Hazardous Substance Facility Response Plans: Compliance Date Delay and Changes To Reflect Administration Policy (Kresmion)</a>